Jump to Content

Meter reading

Every reading on a bill is marked as taken by the metering operator, reported by the customer, or estimated – and estimates must state a reason.

Updated: August 2026

A meter reading is not a consumption figure. The meter keeps counting up from the day it was installed; consumption is only the difference between two readings.

Where the meter reading comes from

And why that is stated on the invoice

  • MSB

    Read by the metering point operator

    A member of staff or the remote reading supplies the value. The most reliable case – and the normal one with intelligent metering systems.

  • KUN

    Read by the customer

    The customer submits the reading by card, portal or app. The utility checks it for plausibility against the history.

  • EST

    Estimated consumption

    Where no value is available, consumption is extrapolated from the previous year. The reason has to appear on the invoice.

Codes for the reason behind an estimate

  • 1Missing data from the customer's own reading
  • 2No access to the metering equipment was possible
  • 3Consumption allocation following a mid-year price change

§ 40 (2) EnWG requires every meter reading to be labelled. An estimate is permitted but has to be justified – and it is the most common trigger for enquiries to customer service.

Reading it correctly#

  • Only the digits before the decimal point count – decimals are usually set off in red
  • On two-rate meters, report both values, HT and NT separately
  • On instrument transformer meters, apply the transformer ratio
  • Digital meters often have to be switched to the right display first – the OBIS code tells you which register you are looking at

When it is estimated#

Where no value is available, consumption is extrapolated from the previous year. That is permitted, but it has to be justified. The usual codes on the invoice:

  1. 1missing data from the customer's own reading
  2. 2no access to the metering equipment was possible
  3. 3consumption allocation following a mid-year price change

Substitute values in metering point operation#

Where a metered value is missing or fails the plausibility check, the metering point operator forms an Ersatzwert (substitute value). The usual methods, in order of preference:

  • Vorjahreswert – the same period of the previous year, temperature-adjusted for gas
  • Vergleichswert – a comparable period of the same metering location, such as the previous week for a load curve
  • Interpolation – for gaps in a load curve, between the last and the next valid value
  • Schätzung nach Lastprofil – annual consumption spread across the period using the standard load profile

Related topics

Sources & further reading