Instalment plans, hardship agreements and securities
The toolkit for customers in payment difficulty: the voluntary instalment plan, the legally mandated hardship agreement before a disconnection, and prepayment, security deposit and prepaid meter as the utility's safeguards.
Between “invoice paid” and “supply disconnected” lies a whole toolbox. It is not only socially intended but also commercially sensible: a disconnection costs money and brings none back. The instruments here do the opposite – provided the billing system can represent them cleanly.
Overview#
| Instrument | Who initiates | When | Legal basis |
|---|---|---|---|
| Ratenzahlungsvereinbarung (instalment agreement) | customer or utility | large back-payment, temporary shortfall | freedom of contract; due dates under § 17 StromGVV / GasGVV |
| Abwendungsvereinbarung (hardship agreement) | utility – must offer | together with the threat of disconnection | § 19 (5) StromGVV / GasGVV |
| Vorauszahlung (prepayment) | utility | justified doubts about ability to pay | § 14 StromGVV / GasGVV |
| Sicherheitsleistung (security deposit) | utility, as an alternative to prepayment | as for prepayment | § 15 StromGVV / GasGVV |
| Vorkassezähler / prepaid meter | utility, customer may consent | instead of prepayment or instead of disconnection | § 14 (3) StromGVV; outside the GVV by contract |
Ratenzahlungsvereinbarung#
The simplest form: a receivable that has fallen due – usually a back-payment from the annual statement – is split into several instalments paid alongside the running Abschläge. Outside basic supply it is not legally required, but almost every utility offers it because it reduces bad debt. Three to twelve instalments are usual, interest-free or with a small surcharge; the agreement normally contains an acceleration clause: miss one instalment and the entire remaining balance falls due immediately.
Abwendungsvereinbarung#
Since the amendment of the basic-supply ordinances the Abwendungsvereinbarung is no longer a goodwill offer but a duty: a basic supplier threatening disconnection must at the same time offer the customer an agreement with which they can avert it. The customer only has to accept – then no disconnection may take place as long as they comply.
An Abwendungsvereinbarung in numbers
- Arrears (instalments due + back-payment)
- €540.00
- Term
- 12 months
- Instalment, interest-free
- €45.00/month
- Running Abschlag
- €115.00/month
Prepayment, security deposit, prepaid#
- Vorauszahlung (§ 14 StromGVV)
- The basic supplier may demand a prepayment for the billing period where the circumstances of the individual case give reason to assume the customer will not meet their payment obligations, or not on time – typically after repeated dunning or a disconnection. It is sized on the consumption of the previous billing period or the average consumption of comparable customers. In practice it is an Abschlag that falls due before rather than after the month of consumption.
- Sicherheitsleistung (§ 15 StromGVV)
- Instead of prepayment the basic supplier may demand a security – a cash deposit or a guarantee. Cash securities bear interest at the base rate; the utility may draw on it if the customer fails to pay despite a reminder, and must return it once the conditions no longer apply. It is not revenue but a liability on the balance sheet.
- Vorkassezähler / prepaid (§ 14 (3) StromGVV)
- Instead of prepayment the basic supplier may install a cash or chip-card meter or a comparable prepaid system – today often a prepaid function of an intelligent metering system. The customer tops up credit, the meter supplies until it is used up. The rule is intended as an alternative to disconnection: the customer keeps control, the utility keeps the default risk only up to the emergency credit.
What the billing system must be able to do#
- The instalment plan as an object in its own right in the contract account: reference to the original receivables, instalment amount, due dates, status per instalment, acceleration clause. The original receivable remains; the plan only replaces its due date.
- Due-date logic: the original receivable must no longer count as overdue while the plan is honoured. If an instalment is missed, the remainder – depending on the agreement – falls due immediately or only after a grace period.
- Dunning block: while an instalment plan or Abwendungsvereinbarung is running, the affected receivables may enter neither the dunning run nor the disconnection threshold. Running instalments, by contrast, continue to be dunned normally.
- Two payment streams: instalment and Abschlag in parallel, with unambiguous assignment of incoming payments – for SEPA ideally as two items or one collection with a defined order of allocation.
- Book securities separately: deposits and prepaid credit are liabilities towards the customer, not payments against receivables – with their own interest and return logic.
- History: how often and when a customer received and honoured an agreement is information in itself – for the next credit check and for the question of whether a prepayment may be demanded.