Format change
Twice a year – on 1 April and 1 October – the German energy market switches its communication formats. With no transition period: anyone who has not migrated can no longer talk to the market.
The formats used in market communication are not set permanently. The Bundesnetzagentur defines them bindingly and replaces them twice a year. At midnight on the deadline the old versions lose their validity – there is no transition period and no leniency.
A format change, from consultation to deadline
Twice a year, always to the same pattern
- Consultationaround 8 months before
- Rulingaround 6 months before
- Deadline1 April or 1 October
- Processes affected
- GPKE, MaBiS, WiM, MPES
- Deadlines
- 1 April and 1 October
- Implementation window
- around 6 months, no transition period
At midnight on the deadline the old versions lose their validity – with no transition period. Anyone who has not migrated can no longer communicate with the market. The roughly six months between the ruling and the deadline are the entire window in which software vendors have to develop and ship and utilities have to implement, test and train.
What gets replaced#
The core energy industry processes are affected – not only the message formats themselves, but the decision trees, code lists and deadlines behind them:
| Abbr. | Process |
|---|---|
| GPKE | Business processes for supplying customers with electricity – supplier switching for power |
| MaBiS | Market rules for electricity balancing group settlement – see balancing groups |
| WiM | Switching processes in metering – changing the metering point operator |
| MPES | Market processes for generating market locations – feed-in, see PV systems |
The cycle#
- 1
Consultation
The EDI@Energy project group submits revised message versions to the Bundesnetzagentur in draft. Around eight months before the deadline, every market participant can comment.
- 2
Ruling
About six months before the deadline the Bundesnetzagentur publishes the final versions in a numbered Mitteilung zu den Datenformaten.
- 3
Implementation
In those six months the software vendor has to develop and ship, and the utility has to implement, test and train. That is the entire window.
- 4
Deadline
On 1 April or 1 October the new versions become binding for all market participants. The old ones stop applying at that moment.
Why this is not a software update#
The most common misconception: “the vendor ships a patch for that.” The patch is the easy part. The real work is the process changes around it – altered decision trees, new mandatory fields, adjusted clearing cases, changed deadlines – and the testing effort:
- Regression, load and security tests
- Cut-over tests and training for the business departments
- Tests with market partners – market communication is bilateral, so coordination has to cross company boundaries
When the deadline does not hold: LFW24#
The 24-hour supplier switch was the largest format change of recent years, and it shows what happens when the six-month window is not enough. The German-speaking SAP user group (DSAG) published survey data on it: the realistic implementation need after the software shipped was around 37 weeks, while the deadline allowed 26. In a survey of 160 energy suppliers, 88 % said they could not complete the work by April 2025.
The Bundesnetzagentur consequently moved the deadline from 4 April to 6 June 2025. A move to 1 October 2025 had been requested – and was rejected.