Switching supplier
Switching supplier changes nothing physically – only which balancing group the site belongs to. Since June 2025 it must be possible within 24 hours.
The customer signs with the new supplier, and everything after that runs between market partners. The customer neither has to terminate anything nor register anything – the new supplier handles it as part of the switching process.
How a supplier switch runs
What happens between the signature and the first invoice
- 1
Day 0
The customer signs the new contract
The new supplier needs the name, the supply address and the market location ID or meter number.
- 2
Day 0–1
Registration with the grid operator
The new supplier registers the supply; the grid operator checks whether the market location belongs to it.
- 3
Day 1
The old supplier is deregistered
The previous supplier is informed and either confirms or objects – for instance where a minimum term is still running.
- 4
from 24 hours
The switch takes effect
Since June 2025 a supplier switch has to be possible within 24 hours. Nothing changes physically – only the assignment within the balancing group.
- 5
afterwards
Final invoice
The old supplier bills up to the switching day; the reading on the key date comes from the metering point operator or from the customer.
The customer notices nothing physically: the same electricity flows through the same grid. What changes is which balancing group the withdrawal point is assigned to – and with it, who procures and bills the energy.
What the new supplier needs#
- The customer's name and supply address
- The market location ID (11 digits including a check digit), or the meter number instead – the MaLo ID can be looked up from address or meter number through the BDEW's MaLo-Ident interface
- The desired start of supply
- Whether this is a switch, a move-in or an substitute supply case
The process#
- 1Registration with the grid operator – the new supplier registers the market location via UTILMD for the desired start date
- 2Termination with the previous supplier – the new supplier terminates the old contract as the customer's authorised representative (Bevollmächtigter)
- 3Confirmation or rejection – grid operator and previous supplier respond; a rejection becomes a clarification case
- 4Assignment in the balancing group – on the key date the market location moves into the new supplier's balancing group
- 5Meter reading transfer – the metering point operator delivers the switch reading via MSCONS
- 6Final invoice from the previous supplier – within six weeks of the end of supply, § 40c EnWG
Grounds for rejection#
| Ground | What happens then |
|---|---|
| An existing minimum term with the previous supplier | The switch is deferred to the end of that term |
| Market location not found | A clarification case – check address and meter number |
| Outstanding receivables with the previous supplier | Not a ground for rejection – a switch may not fail on this |
| Registration for a period already assigned | Rejection due to an existing assignment (Ablehnung wegen bestehender Zuordnung): the earlier registration stands and the later one is rejected – the second supplier has to sort it out with the customer |