Grid connection and installation registration

The physical link between a property and the distribution grid – governed by the NAV – and the path by which a generating installation reaches the grid via installer and grid operator.

Updated: August 2026

Before a meter hangs, a tariff applies or a PV system feeds in, there has to be a grid connection. It is a legal relationship in its own right, with its own contracting parties, its own costs and – for generating installations – its own registration process with statutory deadlines.

The Niederspannungsanschlussverordnung (NAV), the low-voltage connection ordinance, separates the connection itself from its use. That is why, in a rented building, the owner and the tenant have different contracts with the grid operator – without either of them ever having signed one.

Netzanschlussverhältnis (connection relationship)Anschlussnutzungsverhältnis (connection-use relationship)
Contracting partyAnschlussnehmer (connection owner) – normally the property ownerAnschlussnutzer (connection user) – whoever actually uses the connection to draw power, so the tenant too
Subject matterConstruction, operation, modification and maintenance of the house connectionThe right to draw electricity through the connection, or to feed in
How it arisesGrid connection contract, usually with the building applicationImplicitly, by drawing power (§ 3 NAV)
CostsHouse connection costs and BaukostenzuschussNone of its own – grid fees flow through the supplier
EndDismantling or change of ownerMoving out

The connection user is also the contracting party of the metering point operator and the person the supply contract addresses – see customer types.

What the connection costs#

House connection costs (§ 9 NAV)
The actual cost of building or modifying the connection from the street main to the house connection box. The grid operator may charge them – by effort or as a flat rate.
Baukostenzuschuss (§ 11 NAV)
A construction cost contribution towards the upstream grid, sized by the capacity reserved. For standard house connections up to 30 kW of demand many grid operators charge no BKZ; above that it becomes relevant, e.g. heat pump plus wallbox, or commercial sites.
Netzverträglichkeitsprüfung
Before consenting, the grid operator checks whether the line and the local substation can carry the additional load or feed-in. For generating installations this grid compatibility check is the core of the answer to the connection request; it may result in a different connection point or in grid reinforcement.

Generating installations: the connection request under § 8 EEG#

For PV systems, CHP units and other EEG installations the operator has a right to be connected: the grid operator must connect the installation without delay and with priority at the point that is most favourable by voltage level and distance (§ 8 Abs. 1 EEG). In practice the process runs through the distribution grid operator's portal.

  1. 1

    Submit the connection request

    The installer or operator submits location, capacity, inverter and battery data and the desired metering concept – usually in the DSO portal.

  2. 2

    Grid operator's reply

    It must send the applicant a schedule for processing without delay, and at the latest eight weeks after receipt, and provide the necessary information (§ 8 Abs. 5 and 6 EEG). The result is the connection consent with the connection point.

  3. 3

    Installation and commissioning

    An electrical contractor entered in the grid operator's Installateurverzeichnis (installer register, § 13 NAV) builds the installation, commissions it and produces the Inbetriebsetzungsprotokoll (commissioning report) under VDE-AR-N 4105.

  4. 4

    Meter installation

    The metering point operator swaps to a bidirectional meter; from 7 kW an intelligent metering system is mandatory.

  5. 5

    Registration in the MaStR

    Within one month of commissioning in the Marktstammdatenregister – no entry, no feed-in tariff.

Where processes stall#

  • Incomplete applications: the one-month period only starts with a complete request – every missing data sheet resets it
  • Grid reinforcement needed: then the connection slips by months; the operator is entitled to information on scope and schedule
  • Connection owner is not the operator: for a tenant with PV or for Mieterstrom the owner has to consent to the modification of the grid connection
  • Portal diversity: around 850 distribution grid operators with their own portals and forms; uniform interfaces are only emerging step by step