Grid connection and installation registration
The physical link between a property and the distribution grid – governed by the NAV – and the path by which a generating installation reaches the grid via installer and grid operator.
Before a meter hangs, a tariff applies or a PV system feeds in, there has to be a grid connection. It is a legal relationship in its own right, with its own contracting parties, its own costs and – for generating installations – its own registration process with statutory deadlines.
Two legal relationships, two people#
The Niederspannungsanschlussverordnung (NAV), the low-voltage connection ordinance, separates the connection itself from its use. That is why, in a rented building, the owner and the tenant have different contracts with the grid operator – without either of them ever having signed one.
| Netzanschlussverhältnis (connection relationship) | Anschlussnutzungsverhältnis (connection-use relationship) | |
|---|---|---|
| Contracting party | Anschlussnehmer (connection owner) – normally the property owner | Anschlussnutzer (connection user) – whoever actually uses the connection to draw power, so the tenant too |
| Subject matter | Construction, operation, modification and maintenance of the house connection | The right to draw electricity through the connection, or to feed in |
| How it arises | Grid connection contract, usually with the building application | Implicitly, by drawing power (§ 3 NAV) |
| Costs | House connection costs and Baukostenzuschuss | None of its own – grid fees flow through the supplier |
| End | Dismantling or change of owner | Moving out |
The connection user is also the contracting party of the metering point operator and the person the supply contract addresses – see customer types.
What the connection costs#
- House connection costs (§ 9 NAV)
- The actual cost of building or modifying the connection from the street main to the house connection box. The grid operator may charge them – by effort or as a flat rate.
- Baukostenzuschuss (§ 11 NAV)
- A construction cost contribution towards the upstream grid, sized by the capacity reserved. For standard house connections up to 30 kW of demand many grid operators charge no BKZ; above that it becomes relevant, e.g. heat pump plus wallbox, or commercial sites.
- Netzverträglichkeitsprüfung
- Before consenting, the grid operator checks whether the line and the local substation can carry the additional load or feed-in. For generating installations this grid compatibility check is the core of the answer to the connection request; it may result in a different connection point or in grid reinforcement.
Generating installations: the connection request under § 8 EEG#
For PV systems, CHP units and other EEG installations the operator has a right to be connected: the grid operator must connect the installation without delay and with priority at the point that is most favourable by voltage level and distance (§ 8 Abs. 1 EEG). In practice the process runs through the distribution grid operator's portal.
- 1
Submit the connection request
The installer or operator submits location, capacity, inverter and battery data and the desired metering concept – usually in the DSO portal.
- 2
Grid operator's reply
It must send the applicant a schedule for processing without delay, and at the latest eight weeks after receipt, and provide the necessary information (§ 8 Abs. 5 and 6 EEG). The result is the connection consent with the connection point.
- 3
Installation and commissioning
An electrical contractor entered in the grid operator's Installateurverzeichnis (installer register, § 13 NAV) builds the installation, commissions it and produces the Inbetriebsetzungsprotokoll (commissioning report) under VDE-AR-N 4105.
- 4
Meter installation
The metering point operator swaps to a bidirectional meter; from 7 kW an intelligent metering system is mandatory.
- 5
Registration in the MaStR
Within one month of commissioning in the Marktstammdatenregister – no entry, no feed-in tariff.
Where processes stall#
- Incomplete applications: the one-month period only starts with a complete request – every missing data sheet resets it
- Grid reinforcement needed: then the connection slips by months; the operator is entitled to information on scope and schedule
- Connection owner is not the operator: for a tenant with PV or for Mieterstrom the owner has to consent to the modification of the grid connection
- Portal diversity: around 850 distribution grid operators with their own portals and forms; uniform interfaces are only emerging step by step